Israeli official: Development of disputed Qana gas field will take four stages

Lazar Berman is The Times of Israel's diplomatic reporter

Map showing Israel-Lebanon maritime border claims. (AFP News Agency)
Map showing Israel-Lebanon maritime border claims. (AFP News Agency)

The development of the Qana gas field — and the proceeds Israel will receive from the TotalEnergies corporation — will occur in four stages, explains Energy Ministry Director-General Lior Schillat in a briefing.

The exploratory stage will last 2-4 years, during which initial geological surveys and test drillings will be carried out. In order for that stage to begin, Israel and Total must have completed a fundamental agreement about compensation for Israel.

The next step is the estimate stage, in which over 1-2 years further exploratory drilling takes place, and a final investment decision is made. The two sides will agree on the amount of natural gas in the field, how much Israel is to receive for the gas in its waters south of Line 23, and will sign a detailed agreement.

Israel will receive the first payment from Total before any drilling begins. Once the payment is made, the development phase begins, and continues for 4-7 years. Drilling in order to extract the gas is carried out, and pipes are laid down.

The final phase, which takes place over the next 25-50 years, is the extraction, during which Israel continues to receive payments according to an agreed upon timetable.

Most Popular
If you’d like to comment, join
The Times of Israel Community.
Join The Times of Israel Community
Commenting is available for paying members of The Times of Israel Community only. Please join our Community to comment and enjoy other Community benefits.
Please use the following structure: example@domain.com
Confirm Mail
Thank you! Now check your email
You are now a member of The Times of Israel Community! We sent you an email with a login link to . Once you're set up, you can start enjoying Community benefits and commenting.